Configure the Post Later Feature at the Scenario - Role Level

A Designer can configure a feature that allows a Role Processor with the Post role type to schedule a post to process at a specified date and time. The setting can be configured for a specific scenario > role combination. It is at this level that access to the Post Later feature is controlled.

Refer to Schedule a Post for a Specified Date and Time for more information.

Before performing this task, Design a Governance Hierarchy and add a role with the Post role type.

The setting can be configured at the role level and can cascade down to the scenario role level. Refer to Configure the Post Later Feature at the Role Level for more information.

To configure Post Later at the Scenario - Role Level:

  1. Select dspConduct > Design in the Navigation pane.
  2. Click the Scenarios icon for a category.
  3. Click the Roles icon for a scenario.
  4. Click Vertical View for a Post role.
  5. Click the Scheduled Post Allowed check box.