dspTrack™ assigns a task a Waiting on Dependency status if any of the task’s predecessor tasks are not complete and the dependency type is Finish to Start.
dspTrack™ assigns a task a Completed status if the task has valid values for its Actual Start Date and Actual Finish Date.
dspTrack™ assigns a task an In Progress status if the task has a valid Actual Start Date and the Actual Finish Date is NULL.
All other tasks are assigned a status of Ready.