dspTrack

Project Dependency

Use this page to view all dependency types for all tasks in all plan in the project.

To access this page:

  1. Click Track > Project in the Navigation pane.
  2. Click Plans for a project.
  3. Click Vertical View for a plan.
  4. Click the Additional Information tab.
  5. Click the Predecessor Dependency or the Successor Dependency icon.

Field

Description

PREDECESSOR PLAN ID

Displays the name of the plan containing the task that is the predecessor in the dependency relationship.

PREDECESSOR PLAN TASK ID

Displays the name of the task that is the predecessor in the dependency relationship.

SUCCESSOR PLAN ID

Displays the name of the plan containing the task that is the successor in the dependency relationship.

SUCCESSOR PLAN TASK ID

Displays the name of the task that is the successor in the dependency relationship.

DEPENDENCY TYPE ID

Displays the Dependency Type of the dependency relationship. Values are:

  • Start to Finish
  • Start to Start
  • Finish to Start
  • Finish to Finish

Refer to Use Dependency Types for more information.